Day Seventy Four.

Plaster and insulation has been delivered!


We decided to get an independent inspector to go over the frame before the plaster was installed – I was surprised at the amount of items that they picked up! Luckily Porter Davis have been really good with the report and got straight onto fixing the issues!

More timber has also been added to the frame. We were surprised to receive an invoice a few weeks ago saying the frame was ‘complete’ (which we paid) and then to find this was done after the fact. Always make sure you check the work has been 100% completed before you hand over your money – we were lucky that they came back very quickly to fix the parts that were missing but I’m sure not everyone is that lucky!

Day Sixty Six.

Electrical, Gas and Water pipes have been installed. Air con ducts are in and Cavity slider frames have been installed.

Shower base frames have also been installed in both the main bathroom and ensuite. Can’t believe the size of the master shower! Going to be amazing!!